In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communications. According to Metcalfe's Law, a project with 10 stakeholders has__________ potential communication channels.

进入在线模考

参考答案

B

答案解析

参考译文:在沟通需求分析过程中,项目经理应该将可能的沟通渠道或途径的数量看做是一个项目沟通复杂程度的指标。根据梅特卡夫定律,有10个干系人的项目,就有10×(10-1)/2=45条潜在沟通渠道。