单选题
信息系统项目管理师
题号 #1913149
assesses the priority of identified risks using their probability of occurrin9,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance ofthe project consVmnts ofcost,schedule,scope and quality.
参考答案
B
答案解析
参考译文:定性风险分析(Qualitative RiskAnalysis)利用风险发生概率、风险一一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围和质量的风险承受度水平),对已识别风险进行优先级的评估。