题号 #1929184

A project manager is called to an informal meeting with the customer and a problem is raised.This problem has major implications for the project manager's company, but the customer wants to pursue a solution at the meeting.The project manager should(72)

进入在线模考

参考答案

C

答案解析

在项目经理召开的一个非正式会议上,客户临时提出了一个问题。该问题对项目经理的公司会产生较大的影响,且客户要求在会议上给出一个解决方案。项目经理在其公司没有给出解决方案之前,应尽可能多地收集该问题的相关信息(collectasmuchinformationontheproblemwithoutcommittinghiscompanytoasolution)。

你可能感兴趣的试题

A. measure, delay, record, distribute, analyze, and direct
B. plan, schedule, monitor, control, report, and forecast
C. promote, highlight, monitor, control, forecast, and report
D. emphasize, visualize, analyze, conceptualize, report, and record
找试题 · 找答案 · 找资料 在线模考