The case of Boundary Dam project and a series of advancements show that CCS technologies are prepared for its application in the power sector.

进入在线模考

参考答案

D

答案解析


The case of Boundary Dam pro-ject and a series of advancementsshow that CCS technologies areprepared for its application in thepower sector.
 