Which of the following would you do if you wanted the contractor to start work on a project immediately?( )
A.Issue a letter contract, but follow up as soon as possible with some type of a final contract
B.Sign a Time and Materials contract for the entire effort
C.Negotiate a Firm Fixed Price contract
D.Negotiate a cost sharing arrangement
参考答案
A
答案解析
暂无解析