Which of the following would you do if you wanted the contractor to start work on a project immediately?( )
A.Issue a letter contract, but follow up as soon as possible with some type of a final contract
B.Sign a Time and Materials contract for the entire effort
C.Negotiate a Firm Fixed Price contract
D.Negotiate a cost sharing arrangement

进入在线模考

参考答案

A

答案解析