Your project experiences an internal failure of a major component causing project overruns.The action necessary to bring this defect into compliance with specifications is considered: A.Rework
B.Warranty repairs
C.Quality control
D.Preventative

进入在线模考

参考答案

A

答案解析

暂无解析