A project manager states, “I know that the risk exists and am aware of the possible consequences.I am willing to wait and see what happens.I accept the consequences should they occur.” He /she is exercising the method of risk reduction. ( )
A.Transfer
B.Avoidance
C.Mitigation
D.Assumption

进入在线模考

参考答案

D