单选题
PMP
题号 #410907
When evaluating the possible solutions and tradeoffs to resolve a project conflict, the project conflict, the project manager should: ( )
A.Consider only lessons learned from previous projects
B.Ignore the potential of compromising the sponsor’s objectives, and corporate strategic plan
C.Fully consider possible impact on schedule, cost, risk, and performance
D.Consider only the effect on resources consumed and project resource consumption for that project
参考答案
C
答案解析
暂无解析
你可能感兴趣的试题
A.向上自由流
B.水平自由流
C.不受限制的交流
D.项目经理利用其与项目利害相关者的非正式的关系的能力
A.项目办公室备忘录
B.项目办公室指示
C.项目团队会议
D.正式的报告