If a project manager emphasizes those areas where he is in agreement with the functional manager and down plays other conflicts, the project manager can be said to be using which of the following to address the conflict: ( )
A.Withdrawal
B.Smoothing
C.Compromising
D.Confrontation

进入在线模考

参考答案

B