单选题 PMP
题号 #410932

Increasing resources on the critical path activities may not always shorten the length of the project because:( )
A.No activities are time-dependent or resource-dependent
B.Activities are always scheduled with optimal number of resources
C.The Project Manager always selects original resources with the highest skill levels
D.Adding more resources may create additional work and produce inefficiencies

进入在线模考

参考答案

D

答案解析

暂无解析

你可能感兴趣的试题

找试题 · 找答案 · 找资料 在线模考