Increasing resources on the critical path activities may not always shorten the length of the project because:( )
A.No activities are time-dependent or resource-dependent
B.Activities are always scheduled with optimal number of resources
C.The Project Manager always selects original resources with the highest skill levels
D.Adding more resources may create additional work and produce inefficiencies
参考答案
D
答案解析
暂无解析