单选题 PMP
题号 #410953

Upon completion of the plan, your team determines that the schedule developed is too long.An analysis shows that the network diagram cannot be changed.You have additional resources available and some work can be easily shared with additional resources.Your best approach would be to:( )
A.Fast track the project
B.Conduct a Monte Carlo analysis
C.Use a parametric estimate
D.Crash the schedule

进入在线模考

参考答案

D

答案解析

暂无解析

你可能感兴趣的试题

找试题 · 找答案 · 找资料 在线模考