You have estimated and scheduled your project based on the team members you have been assigned and developed the BCWS baseline.However, you have now been assigned new team members who are more experienced and higher salaried than those on which you based your initial estimate.The most probable impact on project performance would be: ( )
A.Negative CV, negative SV 
B.Negative CV, positive SV 
C.Positive CV, negative SV 
D.Positive CV, positive SV

进入在线模考

参考答案

B