Which of the following would not necessarily increase the accuracy of estimating the project cost? ( )
A.Pricing out the work at lower levels in the work breakdown structure
B.Using historical data
C.Talking to people who have worked on similar project
D.Spending additional time on the estimate
参考答案
D
答案解析
暂无解析