单选题 PMP
题号 #410972

Which of the following would not necessarily increase the accuracy of estimating the project cost? ( )
A.Pricing out the work at lower levels in the work breakdown structure 
B.Using historical data 
C.Talking to people who have worked on similar project 
D.Spending additional time on the estimate

进入在线模考

参考答案

D

答案解析

暂无解析

你可能感兴趣的试题

找试题 · 找答案 · 找资料 在线模考