单选题
PMP
题号 #410994
Core planning processes have clear dependencies that require them to be performed in essentially the same order on most projects.Which of the following is the correct order as a portion of core planning processes? ( )
A.Scope planning, scope definition, activity sequencing, activity duration estimation
B.Scope definition, scope planning, activity definition, activity sequencing, activity duration estimation
C.Scope planning, scope definition, activity sequencing, activity definition, activity duration estimation
D.Activity duration estimation, scope planning, scope definition, activity definition, activity sequencing
参考答案
A
答案解析
暂无解析
你可能感兴趣的试题
A.项目执行
B.项目规划
C.项目收尾
D.项目审定
A.项目相关者
B.变更控制委员会
C.领域事务专家
D.项目经理