Changes to a project plan may be inevitable, even with a well-developed scope management plan.Project managers should ensure project stakeholders, especially the project sponsor are aware that ( )
A.The cost of change is higher in the conceptual phase
B.The cost of change is lower in the conceptual phase
C.The value added from a changes is lower in the conceptual phase
D.The cost change is lower in the implementation phase
参考答案
B