单选题
PMP
题号 #411016
Gaining customer acceptance is a detailed process of verifying and documenting project results to ensure the product(s) meets its intended use..This process includes all of the following, except: ( )
A.Preparing, in advance, a strategy about how to close the project
B.Designating a single point of contact for the customer to speak to, when issues arise
C.Modification of the project baseline
D.Providing sufficient instructions for the proper use of the product by the customer
参考答案
C
答案解析
暂无解析