The project team should have a working knowledge of statistical process control to help conduct quality control activities.Of all the topics involved, which of the following is the most important for the team to understand?( )
A.Sampling and probability
B.Attribute sampling and variable sampling
C.Tolerances and control limits
D.Special causes and random causes

进入在线模考

参考答案

A

答案解析

来自于统计过程控制的取样和概率帮助团队调整项目结果以符合相关质量标准,这样可以确定用来减少产生令人不满的结果的原因