单选题 PMP
题号 #411080

As the project manager for a large project, you receive a preliminary press release for your approval before distribution.You are expected to approve the release without comment.Your review identifies a major discrepancy regarding some key project financial estimates that may mislead the intended recipients.As the project manager it is your responsibility to: ( )
A.Inform the project sponsor of the discrepancy and refuse to approve the release 
B.Approve the release but send a memo to the sponsor advising that you are aware of the discrepancy and will refer any questions you have received to the sponsor 
C.Approve the release as requested 
D.Completely rewrite the press release and include the correct information

进入在线模考

参考答案

A

答案解析

确保每个客户的利益不受损害是项目经理的基本职责