某项目现金流量如表所示,则项目的静态投资回收期为( )年。

参考答案
C
答案解析
静态投资回收期=(累计净现金流量出现正值的年数-1)+上一年累计净现金流量的绝对值/出现正值年份净现金流量=(4-1)+|200+300+400-900|/400=3。