The cost performance index(CPI) is the ratio of earned value to (73) and can be used to estimate the projected cost of completing the project.

进入在线模考

参考答案

D

答案解析

翻译:成本绩效指数是挣值和(73)的比率,用来估算完成整个工程的预计费用。
A.成本差值B.计划成本C.计划值D.实际花费