题号 #1929183

The project manager must maintain an effective communication link With the customer's satisfaction with the progress of the project. The project manager maintains this link through(71)

进入在线模考

参考答案

A

答案解析

项目经理必须保持一个有效的沟通渠道,以使客户对项目的进展表示满意。项目经理可以通过定期的项目报告(periodicprojectreports)、定期走访客户(pefiodicvisitstothecustomer)和电话交流(telephonicexchanges)等保持这个渠道。

你可能感兴趣的试题

A. tell the customer that he will not address any problems becausethis is only an information exchange meeting
B. tell the customer that the problem is not sufficiently defined to determine the appropriate action
C. collect as much information on the problem without committing his company to a solution
D. give the customer a range of solutions that might be acceptable to his company
A. measure, delay, record, distribute, analyze, and direct
B. plan, schedule, monitor, control, report, and forecast
C. promote, highlight, monitor, control, forecast, and report
D. emphasize, visualize, analyze, conceptualize, report, and record
找试题 · 找答案 · 找资料 在线模考