单选题
PMP
题号 #410882
When the risk event probabilities are multiplied by their respective estimated risk event values (in dollars) and are then added together, the sum represents the: ( )
A.Project manager ’s risk aversion quotient
B.Total project risk events
C.Expected monetary value of the project’s risk
D.Scope planning
参考答案
C
答案解析
暂无解析