When the risk event probabilities are multiplied by their respective estimated risk event values (in dollars) and are then added together, the sum represents the: ( )
A.Project manager ’s risk aversion quotient
B.Total project risk events
C.Expected monetary value of the project’s risk
D.Scope planning

进入在线模考

参考答案

C