The project proceeded successfully until the customer asked for additional work not included in the contract.At that point the project team began to make changes to the specifications, delivery date, and schedule.What communication device should the project manager have demanded before any work was modified? ( )
A.Meeting with the sponsor
B.Formal, written correspondence with the customer
C.Memo from the customer
D.Memo to the customer

进入在线模考

参考答案

B