In a start-to-start relationship between two tasks not on the critical path, the project team determines that the start of the successor task must be delayed 3 days after the start of its predecessor.This delay is referred to as( )
A.Slack
B.Free float
C.Level float
D.Lag

进入在线模考

参考答案

D

答案解析

暂无解析