In some Arrow Diagramming Method (ADM) networks, the project manager may be required to indicate logic relationships that do not consumer resources or time.These relationships are shown by using:( )
A.Critical path activities
B.Non-critical path activities
C.Slack time activities
D.Dummy activities

进入在线模考

参考答案

D