单选题
PMP
题号 #410948
Management has decided to “crash” a project in order to avoid penalty payments for late deliveries.Additional costs are expected.To crash the project, either overtime or additional resources should be assigned to:( )
A.All activities
B.Only those activities with the longest time durations C.Those activities on the critical path beginning with the lowest additional cost activities
D.Those activities with the greatest degree of risk
参考答案
C
答案解析
暂无解析