单选题 PMP
题号 #410948

Management has decided to “crash” a project in order to avoid penalty payments for late deliveries.Additional costs are expected.To crash the project, either overtime or additional resources should be assigned to:( )
A.All activities
B.Only those activities with the longest time durations C.Those activities on the critical path beginning with the lowest additional cost activities
D.Those activities with the greatest degree of risk

进入在线模考

参考答案

C

答案解析

暂无解析

你可能感兴趣的试题

找试题 · 找答案 · 找资料 在线模考