单选题 PMP
题号 #410951

In building a ship, the painting task can be started but cannot be completed until all plumbing has been completed.This is an example of a:( )
A.Start to finish relationship
B.Finish to finish relationship
C.A relationship that shows slack
D.A finish to start relationship

进入在线模考

参考答案

B