单选题 PMP
题号 #410990

A project manager estimates a project will take 14 weeks at a cost of $60,000.In signing the contract documents, the customer imposes a penalty for late completion of $2,000 per estimates that the maximum possible crashing of the project duration is 4 weeks, at an additional cost of $9,000.Assuming that the project manager is going to make the decision and that cost is the driving criteria for the project manager’s organization, what is the expected project cost? ( )
A.$69,000
B.$71,000
C.$70,000
D.$62,000

进入在线模考

参考答案

C

答案解析

暂无解析