The work breakdown structure is an excellent tool for objective control and evaluation.Which of the following is generally not validated through the WBS?( )
A.Time, schedule, and cost
B.Management coordination and organizational structuring
C.Risk and impact of decision-making
D.Quality of the work

进入在线模考

参考答案

D

答案解析

暂无解析