单选题 PMP
题号 #411060

During the first half of the project.five team members left for other projects without being replaced.two team members went on vacation without informing you.and other team members expressed uncertainty about the work they were to complete.In this situation.it is BEST if you create a _____for the second half of the project.
A.work breakdown structure
B.resource histogram
C.staffing management plan
D.responsibility matrix

进入在线模考

参考答案

C

答案解析

人员配备管理计划描述了资源何时获取和如何离开。