单选题 PMP
题号 #411064

You are working on the cost budget for one project.Which of the following is true?( )
A.This process assigns cost estimates to project activities including risks and contingency plans.
B.The cost baseline will be used to measure variances and future project performance.
C.This process assigns cost estimates for expected future period operating costs.
D.The cost baseline is the expected cost for the project.

进入在线模考

参考答案

B

答案解析

将来的周期运行成本被认为是运行成本,不是项目成本的一部分

你可能感兴趣的试题

找试题 · 找答案 · 找资料 在线模考