单选题
系统集成项目管理师
题号 #1929171
某系统集成公司制订了一系列完备的质量管理制度,其中一项是要求每个项目在各个阶段的最后都必须进行质量审计。这种审计活动是(70)过程的一部分工作。
参考答案
A
答案解析
项目质量审计是一种独立的结构化审查,用来确定项目活动是否遵循了组织和项目的政策、过程与程序。它是实施项目质量保证过程的一部分工作。
你可能感兴趣的试题
A.
periodic project reports,periodic visits to the customer, and telephonic exchanges
B.
subordinates,project team members,and the project sponsor
C.
one-time reports,weekly reports,and monthly reports
D.
the telephone,facsimile,and data transmission
A.
tell the customer that he will not address any problems becausethis is only an information exchange meeting
B.
tell the customer that the problem is not sufficiently defined to determine the appropriate action
C.
collect as much information on the problem without committing his company to a solution
D.
give the customer a range of solutions that might be acceptable to his company
A.
measure, delay, record, distribute, analyze, and direct
B.
plan, schedule, monitor, control, report, and forecast
C.
promote, highlight, monitor, control, forecast, and report
D.
emphasize, visualize, analyze, conceptualize, report, and record