单选题
PMP
题号 #411063
An activity has an early start date-of the 10th and a late start date of the 19th.The activity also has a duration of 4 days.There are no nonworkdays.From the information given, what can be concluded about the activity?( )
A.Total float for the activity is 9 days.
B.The early finish date of the activity is the end of the day on the 14th.
C.The late finish date is the 25th.
D.The activity can be completed in 2 days if the resources devoted to it are doubled
参考答案
A
答案解析
计算总的浮动时间的公式是用活动完成最迟的时间减去最早的时间,即19-10=9
你可能感兴趣的试题
A.这个过程分配成本预算给包括风险和应急计划在内的项目活动
B.成本基线用于评估偏差和将来的项目绩效
C.这个过程分配成本预算给将来的周期运行成本
D.成本基线是项目成本的期望值
A.取样和概率
B.属性取样和变量取样
C.公差和控制限度
D.特别原因和随机原因