单选题 PMP
题号 #411063

An activity has an early start date-of the 10th and a late start date of the 19th.The activity also has a duration of 4 days.There are no nonworkdays.From the information given, what can be concluded about the activity?( )
A.Total float for the activity is 9 days.
B.The early finish date of the activity is the end of the day on the 14th.
C.The late finish date is the 25th.
D.The activity can be completed in 2 days if the resources devoted to it are doubled

进入在线模考

参考答案

A

答案解析

计算总的浮动时间的公式是用活动完成最迟的时间减去最早的时间,即19-10=9